Order of the National Green Tribunal regarding construction of reverse osmosis plants at Balotra and Jasol CETPs, Rajasthan, 22/12/2015

  • 22/12/2015

Order of the National Green Tribunal in the matter of Digvijay Singh Vs. State of Rajasthan & Ors. dated 22/12/2015 regarding extension of time to comply with the order of the Tribunal in relation to construction of R.O plants of 2.5 MLD and 6 MLD capacity at Balotra and Jasol CETPs respectively.

Applications allowed and time granted to the applicant to install both the ROs by 31st January, 2016. NGT also made it clear that if the RO plants are not constructed and become operational by 31st January, 2016 the applicants would be liable to pay a sum of Rs. Five Lakh as cost each.