Order of the National Green Tribunal regarding construction and completion of barrage in Madhya Pradesh, 29/01/2014

  • 29/01/2014

Order of the National Green Tribunal in the matter of Sanjay Khare Vs. Union of India & Ors. dated 29/01/2014 regarding construction and completion of barrage in Madhya Pradesh. The NGT order states that "Construction and completion of barrage does not require environmental clearance as stated by MoEF. To ensure that there is a proper passage of fishes from the barrage to the downstream, the Project Proponent shall construct a fish pass at its own cost".