First batch of solar mission projects delayed

First batch of solar mission projects delayed About half the projects miss deadline. A number of power projects taken up under the first phase of the Jawaharlal Nehru National Solar Mission (JNNSM) are running behind schedule. A survey by Delhi non-profit Centre for Science and Environment shows many projects in the first batch of phase I, totalling 150 MW of Solar Photovoltaic (PV) power capacity, have missed their January 10, 2012 deadline. Thirty projects of 5 MW capacity each were auctioned in November 2010 and contracts had been signed on January 10, 2011 with a 12 month deadline. The projects are to receive between Rs 11-12 per unit power for 25 years of operation and are expected to provide about 6,570 MWh per year per plant. for full text: http://www.downtoearth.org.in/content/first-batch-solar-mission-projects-delayed