Works to be ready by June

Over 90 per cent of the Rs 8.21 crore project to close the Beki embankment breach at Narayanguri is complete by now, while the rate of erosion is reduced considerably at Bahari in Barpeta district. Highly-placed sources in the State Water Resources Department (WRD) told this newspaper that by June 15 the rest of the work was expected to be complete. Meanwhile, a sanction of Rs 5 crore has been granted for opening the silted up mouth of the Manas at Mathanguri. The BTAD is to execute the work by excavating the mouth of the Manas, sources said.